Mass Haul Planning Exercise

 February 13, 2016     No comments   

Mass Haul Planning Exercise
Instructions
Download the following file from moodle - Civil 2 eworks planning exercise.dwg Plot an A1 copy of Layout 1.
The drawing file contains the centre line longitudinal section of a proposed new road showing the existing ground profile and proposed road profile. The attached table lists the cross sectional areas at the indicated chainages.
Prepare a Mass Haul diagram for the works and prepare a suitable earthworks plan for 3 of the main hauls.
The mass haul diagram should be drawn below the Long section on the plotted A1 drawing sheet.
As a condition of the contract all available cut material must be used to make up fill embankments before bringing on site any external import materials. The contractor has sourced a suitable site for importing suitable materials and also disposing of surplus materials alongside the new road at chainage 3400.
In your earthworks plan for the 3 required hauls list maximum distances in each case and also the amount of material to be moved in each haul.
The cuts consist of the following materials:- (all cut material is deemed as acceptable for fill use)
Cut 1 - Stiff Clay
Cut 2 - Soft Rock
Cut 3 - Common Earth
Cut 4 - Stiff Clay
The method of operation is to be via excavators and dump trucks. For each Haul, the earthworks plan should include the plant resources (excs and dumpers) used and the total time required for each operation.
Yours submission should include:
1. A1 drawing showing the long section and your plotted mass haul diagram (these should show all movements of materials and haul distances.
2. An eworks plan listing 3 main hauls, quoting the amount of material being moved, the haul including Ch to and from and distance, the plant utilized and the time to carry each haul out. (include all calculations).
1
Civil Engineering Construction 3 - Earthworks
  • Share This:  
  •  Facebook
  •  Twitter
  •  Google+
  •  Stumble
  •  Digg
Email ThisBlogThis!Share to XShare to Facebook
Newer Post Older Post Home

0 comments:

Post a Comment

Click Here to Place order

Popular Posts

  • A “criminal minds” Aileen Wournos individual will be your “patient”
     A “criminal minds” Aileen Wournos individual will be your “patient”  A brief history of the patient including diagnoses (documented or your...
  • CEO Jane Lionel has some hard decisions to make with regard to some of the company’
     CEO Jane Lionel has some hard decisions to make with regard to some of the company’solder hands, and even on the eve of that decision, I be...
  • Problem in Supply Chain
    Problem in Supply Chain Problem 2. (Chapter 11: The Storage and Handling System) Compare the constrast private ownership of storage space to...

Recent Posts

Unordered List

Pages

  • Home

Text Widget

Blog Archive

  • November 2022 (20)
  • October 2022 (50)
  • September 2022 (119)
  • August 2022 (107)
  • February 2022 (501)
  • January 2022 (443)
  • December 2021 (488)
  • November 2021 (1574)
  • October 2021 (28)
  • September 2021 (11)
  • July 2021 (8)
  • June 2021 (15)
  • May 2021 (39)
  • April 2021 (15)
  • March 2021 (303)
  • February 2021 (712)
  • January 2021 (903)
  • December 2020 (2)
  • September 2020 (33)
  • April 2016 (5183)
  • March 2016 (3763)
  • February 2016 (4356)
  • January 2016 (1749)
  • December 2015 (22)
  • November 2015 (147)
  • October 2015 (23)

Sample Text

Copyright © STUDYSHIELDS ASSIGNMENT HELP | Powered by Blogger
Design by Hardeep Asrani | Blogger Theme by NewBloggerThemes.com | Distributed By Gooyaabi Templates