Operations Management Questions
The levels of Capacity Planning as they line up with the ERP business model (top to bottom) are:
Rough Cut Capacity Planning, Capacity Requirements Planning, Resource Planning, Detailed Capacity Planning
Strategic Planning, Rough Cut Capacity Planning, Detailed Capacity Planning
Strategic Planning, Rough Cut Capacity Planning, Resource Planning, CRP
Strategic Planning, Resource Planning, Rough Cut Capacity Planning, CRP
RCCP (Rough Cut Capacity Planning) is a top management planning process.
True
False
Detailed Capacity Planning and CRP (Capacity Requirements Planning) are basically the same process.
True
False
Detailed Capacity Planning and CRP (Capacity Requirements Planning) are basically the same process.
True
False
Resource Planning is a top management planning activity owned by top management. It is typically prepared for them by others in the organization but reviewed and approved by top management.
True
False
The levels of Capacity Planning as they line up with the ERP business model (top to bottom) are:
Rough Cut Capacity Planning, Capacity Requirements Planning, Resource Planning, Detailed Capacity Planning
Strategic Planning, Rough Cut Capacity Planning, Detailed Capacity Planning
Strategic Planning, Rough Cut Capacity Planning, Resource Planning, CRP
Strategic Planning, Resource Planning, Rough Cut Capacity Planning, CRP
RCCP (Rough Cut Capacity Planning) is a top management planning process.
True
False
Detailed Capacity Planning and CRP (Capacity Requirements Planning) are basically the same process.
True
False
Detailed Capacity Planning and CRP (Capacity Requirements Planning) are basically the same process.
True
False
Resource Planning is a top management planning activity owned by top management. It is typically prepared for them by others in the organization but reviewed and approved by top management.
True
False