Earned Value Analysis
A given project has a BAC = $10,000, PV(cumulative to date) = $5,000, AC(cumulative to date) = $6,000, and EV(cumulative to date) = $5,500. What is the CSI?
0.00
0.92
1.01
1.13
A given project has a BAC = $10,000, PV(cumulative to date) = $5,000, AC(cumulative to date) = $6,000, and EV(cumulative to date) = $5,500. What is the CSI?
0.00
0.92
1.01
1.13